Phase I Construction Timeline


Summer 2014
  • High School Boiler Replacement (Completed)
  • Exterior Brick replacement at Wealthy Elementary (Completed)

 

Spring 2015

  • Begin construction on new main entrances at Breton Downs, Wealthy, and Woodcliff Early Childhood Center(Completed)
  • Begin renovations of Learning Commons at the three elementary schools (Completed)
  • Begin construction of new restrooms for Woodcliff Early Childhood Center (Completed)
  • Begin replacement of district mechanical control systems (Completed)

 

Summer 2015

  • Replacement and enhancement of security cameras and card reader access for exterior doors in all buildings (Completed)
  • Complete construction of new main entrances at Breton Downs, Wealthy, and Woodcliff Early Childhood Center (Completed)
  • Start and complete remodeling of Lakeside elementary main office and main entrance (Completed)
  • Complete renovations of Learning Commons at the three elementary schools
  • Complete construction of new restrooms for Woodcliff Early Childhood Center (Completed)
  • Complete replacement of district mechanical control systems (Completed)

 

Spring 2016

  • Begin construction of new main entrance at the high school (Completed)
  • Begin renovations of Learning Commons at the middle school and high school (Completed)

 

Summer 2016

  • Complete renovations of the middle school Learning Commons
  • Complete construction of the new main entrance and Learning Commons renovations at the high school